Maldives Transport and Contracting Company (MTCC) on Thursday, 01st July revealed their progress of Isdhoo harbor development project.
According to the contractor, the work on design and build of the island’s harbor has observed an overall 90% progress. MTCC had also attested on completing the concrete works for the harbor’s walkway bridge the previous day, 30 June.
Meanwhile, MTCC is installing the harbor pavement which itself has observed 72% completion.
The project components include dredging and excavation operations of 27,129 cubic meters along with the construction of a quay wall measuring 230 meters and a breakwater measuring 208 meters.
Among other structural developments, MTCC will further develop a 98-meter revetment as well as install a paved area of 1,560 square meters.
Miscellaneous arrangements, contractually obligatory for MTCC also include, installation of harbor lights.
According to the contractor the project value is a total of MVR34.7 million, while project completion details have not been disclosed in their latest update.