Maldives Transport and Contracting Company (MTCC) on Monday, 05th July, confirmed progress on Kaafu atoll Dhoonidhoo harbor redevelopment and reclamation project.
According to the contractor, they are executing the sheet piling required for the construction of the quay wall under the project. Moreover, MTCC confirmed the overall project has observed 85% progress.
The harbor redevelopment and reclamation project consists of dredging and excavation operations of 4.61 acres and reclamation of 3.75 acres.
Additional aspects of the project include construction of a breakwater, revetment and the quay wall spanning 370 meters, 620 meters and 250 meters respectively. Furthermore, MTCC will develop and install a 250-meter paved area along with the installation of harbor lights.
The project contractor revealed the redevelopment and reclamation project is worth MVR51.4 million.