Maldives Transport and Contracting Company (MTCC) on Sunday, 04th July revealed their progress of Baa atoll Fulhadhoo harbor development project.
According to MTCC, the work on build and design of the harbor project at the island is currently well underway with an overall 87% progress.
Moreover, MTCC on Sunday confirmed they are currently constructing the breakwater under the project, which had officially commenced on 28th June 2021. Additionally, the contractor is installing the harbor pavement as well.
Scope of work for the project includes dredging operations spanning 51,861.5 cubic meters along with the construction of a 223-meter quay wall and a 108-meter breakwater, the latter of which is currently in progress.
Furthermore, other components of the project include installation of a 558-square meter paved area which is at ongoing status while the contractor will install navigation and street lights.
According to MTCC the project valuation is a total of MVR49.4 million.