Maldives Transport and Contracting Company (MTCC) has reported updates on double shore protection projects in two local islands.
The contracting corporation reveals that the shore protection project in Baa atoll Dharavandhoo has observed 56% progress, and the breakwater profiling works of Kaafu Bandos commenced on the South-East side of the island.
MTCC on Monday, 18th July, confirmed delivery of the second shipment of rock boulders to the project site.
Project scope of Dharavandhoo shore protection include 10,800 cubic-meters of beach filling, construction of 490-meters breakwater and 96 meters of revetment. The recently commenced shore protection endeavor at Bandos involve construction of a 557 meters breakwaters.