Tuesday, 03rd August – the harbor development project at Haa Alif atoll Ihavandhoo observes an overall 57% progress, reports Maldives Transport and Contracting Company (MTCC).
Moreover, the contractor affirms commencing the casting works for the old harbor’s pavement on Monday, 02nd August.
![](https://mbt.mv/wp-content/uploads/2023/07/MBT-1110x200-1-1.png)
The project scope includes dredging and excavation operations spanning 30,509 cubic meters along with the construction of a 95 meter quay wall and a 284 meter breakwater as well as a 178 meter revetment.
Additionally, MTCC will install both navigation and street lights as well as construct a pavement area spanning 4,582 square meters.
MTCC reports the project valuation at a total of MVR51.7 million.