Close Menu
Maldives Business TimesMaldives Business Times
    What's Hot

    State Recovers MVR 800M in Outstanding Revenue

    April 29, 2026

    Malé Hospitals Move to Strengthen Backup Power Capacity

    April 29, 2026

    Minister Denies Political Motive Behind Gedhoruveriyaa Housing Delays

    April 29, 2026
    Facebook X (Twitter) Instagram
    Wednesday, April 29
    Facebook X (Twitter) Instagram
    Maldives Business TimesMaldives Business Times
    • Home
    • Features

      State Recovers MVR 800M in Outstanding Revenue

      April 29, 2026

      Malé Hospitals Move to Strengthen Backup Power Capacity

      April 29, 2026

      Minister Denies Political Motive Behind Gedhoruveriyaa Housing Delays

      April 29, 2026

      Dr. Ali Azwar Takes the Helm at STELCO as New Managing Director

      April 28, 2026

      WMO Warns of Rising Likelihood of El Niño in 2026, Raising Global Climate Concerns

      April 27, 2026
    • BUSINESS

      Malé Hospitals Move to Strengthen Backup Power Capacity

      April 29, 2026

      Dr. Ali Azwar Takes the Helm at STELCO as New Managing Director

      April 28, 2026

      Government Targets 33% Renewable Energy Shift to Cut State Spending

      April 26, 2026

      MindCo Marks Girls in ICT Day with Consultative Session in Hulhumalé

      April 26, 2026

      Allied Insurance Launches “Share the Run” Giveaway Ahead of Hulhumalé Run 2026

      April 26, 2026
    • FINANCE
    • OPINION
    • TRAVEL & TOURISM
    • PUBLIC SECTOR
    • LIFE STYLE
    Maldives Business TimesMaldives Business Times
    Home » Lhaimagu harbor dredging works at 88% completion

    Lhaimagu harbor dredging works at 88% completion

    July 4, 20211 Min Read
    Share
    Facebook Twitter LinkedIn Pinterest Email

    MTCC on Sunday, 04th July revealed details on Shaviyani atoll Lhaimagu harbor development project.

    According to the contractor, they are currently executing the dredging works which has already observed 88% completion.

    The project scope entails dredging and excavation operations of 31,000 cubic meters along with the construction of a breakwater, quay wall and revetment spanning 350-meters, 276-meters and 500-meters respectively.

    Other components include installation of a 1,380 square meter pavement along with the installation of navigation and street lights. The project total is MVR56.3 million.

    Related Posts

    BUSINESS

    Malé Hospitals Move to Strengthen Backup Power Capacity

    April 29, 2026
    BUSINESS

    Dr. Ali Azwar Takes the Helm at STELCO as New Managing Director

    April 28, 2026
    BUSINESS

    Government Targets 33% Renewable Energy Shift to Cut State Spending

    April 26, 2026
    Leave A Reply Cancel Reply

    Don't Miss
    BUSINESS

    Malé Hospitals Move to Strengthen Backup Power Capacity

    April 29, 2026

    Malé City Group of Hospitals has launched a strategic push to expand backup power capacity…

    Minister Denies Political Motive Behind Gedhoruveriyaa Housing Delays

    April 29, 2026

    Dr. Ali Azwar Takes the Helm at STELCO as New Managing Director

    April 28, 2026
    Demo
    Facebook X (Twitter) Instagram LinkedIn Telegram
    • Home
    • BUSINESS
    • PUBLIC SECTOR
    • TRAVEL & TOURISM
    © 2026 Maldives Business Times. by hyvemedia.

    Type above and press Enter to search. Press Esc to cancel.