Saturday, 17th July – Chief Executive Officer of Maldives Transport and Contracting Company (MTCC), Mr. Adam Azim paid a visit to the site of Haa Alif Hoarafushi ferry terminal project site for inspection.
The MTCC front-man had paid the visit to the project site to assess and inspect the progress of the ferry terminal project.
Meanwhile, MTCC on the same day had confirmed the project has already observed an overall 63% progress.
During his visit to Hoarafushi, Mr. Azim had also visited the site of the coastal protection project which is also carried out under MTCC’s wing.
The Hoarafushi coastal protection project entails laying geo-bag revetments at a length of 280-meters. Moreover, the said project has observed 13% progress given its relatively recent commencement.