Close Menu
Maldives Business TimesMaldives Business Times
    What's Hot

    Inflation hikes 0.95 percent annually in 2025

    January 25, 2026

    New social housing scheme attracts over 1600 applications on first week

    January 25, 2026

    BML enables Bulk Payment Services for businesses

    January 25, 2026
    Facebook X (Twitter) Instagram
    Wednesday, January 28
    Facebook X (Twitter) Instagram
    Maldives Business TimesMaldives Business Times
    • Home
    • Features

      Inflation hikes 0.95 percent annually in 2025

      January 25, 2026

      New social housing scheme attracts over 1600 applications on first week

      January 25, 2026

      BML enables Bulk Payment Services for businesses

      January 25, 2026

      Maldives government collects MVR 483 mn as Zakat in five years

      January 23, 2026

      Visit Maldives promotes tourism at Fitur 2026 in Madrid

      January 22, 2026
    • BUSINESS

      Inflation hikes 0.95 percent annually in 2025

      January 25, 2026

      BML enables Bulk Payment Services for businesses

      January 25, 2026

      STO Constructions’ “Roadha Sale” commences

      January 22, 2026

      BML partners with AICB for banking sector development initiative

      January 19, 2026

      Crown and Champa Resorts announces bold new employee-uplifting move: salaries in USD

      January 14, 2026
    • FINANCE
    • OPINION
    • TRAVEL & TOURISM
    • PUBLIC SECTOR
    • LIFE STYLE
    Maldives Business TimesMaldives Business Times
    Home ยป Ungoofaaru road construction project at 85% progress

    Ungoofaaru road construction project at 85% progress

    MTCC reports overall 85% progress of Ungoofaaru road development project
    August 3, 20211 Min Read
    Share
    Facebook Twitter LinkedIn Pinterest Email

    Tuesday, 03rd August – Maldives Transport and Contracting Company (MTCC) reports on latest updates of Raa atoll Ungoofaaru road development project.

    According to the contractor, the project has observed an 85% progress so far while they have completed subgrade works of the carriageway. Meanwhile, MTCC is executing the installation of the aggregate base course (ABC layer) with 95% progress

    Work scope of the project include construction of roads across the island spanning a total area of 16,488 square meters which will include installation of ABC layer and subgrade works in the same area.

    Additionally, MTCC will install a storm-water management system as part of the project while the contractor reports a project valuation of MVR28.02 million.

    Related Posts

    BUSINESS

    Inflation hikes 0.95 percent annually in 2025

    January 25, 2026
    BUSINESS

    BML enables Bulk Payment Services for businesses

    January 25, 2026
    BUSINESS

    STO Constructions’ “Roadha Sale” commences

    January 22, 2026
    Leave A Reply Cancel Reply

    Don't Miss
    Government

    New social housing scheme attracts over 1600 applications on first week

    January 25, 2026

    According to the Ministry of Construction, Housing and Infrastructure, more than 1600 applications have been…

    BML enables Bulk Payment Services for businesses

    January 25, 2026

    Maldives government collects MVR 483 mn as Zakat in five years

    January 23, 2026
    Demo
    Facebook X (Twitter) Instagram LinkedIn Telegram
    • Home
    • BUSINESS
    • PUBLIC SECTOR
    • TRAVEL & TOURISM
    © 2026 Maldives Business Times. by hyvemedia.

    Type above and press Enter to search. Press Esc to cancel.