Close Menu
Maldives Business TimesMaldives Business Times
    What's Hot

    Inflation hikes 0.95 percent annually in 2025

    January 25, 2026

    New social housing scheme attracts over 1600 applications on first week

    January 25, 2026

    BML enables Bulk Payment Services for businesses

    January 25, 2026
    Facebook X (Twitter) Instagram
    Sunday, January 25
    Facebook X (Twitter) Instagram
    Maldives Business TimesMaldives Business Times
    • Home
    • Features

      Inflation hikes 0.95 percent annually in 2025

      January 25, 2026

      New social housing scheme attracts over 1600 applications on first week

      January 25, 2026

      BML enables Bulk Payment Services for businesses

      January 25, 2026

      Maldives government collects MVR 483 mn as Zakat in five years

      January 23, 2026

      Visit Maldives promotes tourism at Fitur 2026 in Madrid

      January 22, 2026
    • BUSINESS

      Inflation hikes 0.95 percent annually in 2025

      January 25, 2026

      BML enables Bulk Payment Services for businesses

      January 25, 2026

      STO Constructions’ “Roadha Sale” commences

      January 22, 2026

      BML partners with AICB for banking sector development initiative

      January 19, 2026

      Crown and Champa Resorts announces bold new employee-uplifting move: salaries in USD

      January 14, 2026
    • FINANCE
    • OPINION
    • TRAVEL & TOURISM
    • PUBLIC SECTOR
    • LIFE STYLE
    Maldives Business TimesMaldives Business Times
    Home ยป Shore protection project of Dhihdhoo observes 73% progress

    Shore protection project of Dhihdhoo observes 73% progress

    MTCC reports overall 73% progress of Dhihdhoo shore protection project
    September 15, 20211 Min Read
    Share
    Facebook Twitter LinkedIn Pinterest Email

    Wednesday, 15th September – Maldives Transport and Contracting Company reports on the latest progress of Haa Alif atoll Dhihdhoo shore protection project.

    As per the contractor, the design and build of the shore protection structures of the island is at ongoing capacity with an overall 73% project progress.

    Moreover, the project scope includes backfilling of 7,750 cubic meters of sand, 1,926 cubic meters of sand for geo-bag filling and the construction of a 310 meter geo-bag revetment to prevent coastal erosion.

    The project value is reported at a total of MVR10.02 million.

    Related Posts

    BUSINESS

    Inflation hikes 0.95 percent annually in 2025

    January 25, 2026
    BUSINESS

    BML enables Bulk Payment Services for businesses

    January 25, 2026
    BUSINESS

    STO Constructions’ “Roadha Sale” commences

    January 22, 2026
    Leave A Reply Cancel Reply

    Don't Miss
    Government

    New social housing scheme attracts over 1600 applications on first week

    January 25, 2026

    According to the Ministry of Construction, Housing and Infrastructure, more than 1600 applications have been…

    BML enables Bulk Payment Services for businesses

    January 25, 2026

    Maldives government collects MVR 483 mn as Zakat in five years

    January 23, 2026
    Demo
    Facebook X (Twitter) Instagram LinkedIn Telegram
    • Home
    • BUSINESS
    • PUBLIC SECTOR
    • TRAVEL & TOURISM
    © 2026 Maldives Business Times. by hyvemedia.

    Type above and press Enter to search. Press Esc to cancel.