Close Menu
Maldives Business TimesMaldives Business Times
    What's Hot

    Government Expands Subsidized Fuel Stations for Fishermen to Nine Locations

    April 29, 2026

    State Recovers MVR 800M in Outstanding Revenue

    April 29, 2026

    Malé Hospitals Move to Strengthen Backup Power Capacity

    April 29, 2026
    Facebook X (Twitter) Instagram
    Thursday, April 30
    Facebook X (Twitter) Instagram
    Maldives Business TimesMaldives Business Times
    • Home
    • Features

      Government Expands Subsidized Fuel Stations for Fishermen to Nine Locations

      April 29, 2026

      State Recovers MVR 800M in Outstanding Revenue

      April 29, 2026

      Malé Hospitals Move to Strengthen Backup Power Capacity

      April 29, 2026

      Minister Denies Political Motive Behind Gedhoruveriyaa Housing Delays

      April 29, 2026

      Dr. Ali Azwar Takes the Helm at STELCO as New Managing Director

      April 28, 2026
    • BUSINESS

      Government Expands Subsidized Fuel Stations for Fishermen to Nine Locations

      April 29, 2026

      Malé Hospitals Move to Strengthen Backup Power Capacity

      April 29, 2026

      Dr. Ali Azwar Takes the Helm at STELCO as New Managing Director

      April 28, 2026

      Government Targets 33% Renewable Energy Shift to Cut State Spending

      April 26, 2026

      MindCo Marks Girls in ICT Day with Consultative Session in Hulhumalé

      April 26, 2026
    • FINANCE
    • OPINION
    • TRAVEL & TOURISM
    • PUBLIC SECTOR
    • LIFE STYLE
    Maldives Business TimesMaldives Business Times
    Home » Ukulhas harbor project observes 62% progress

    Ukulhas harbor project observes 62% progress

    MTCC reports on latest updates of Ukulhas harbor development project
    August 14, 20211 Min Read
    Share
    Facebook Twitter LinkedIn Pinterest Email

    Saturday, 14th August – Maldives Transport and Contracting Company (MTCC) reports on the latest updates of Alif Alif Ukulhas harbor development project.

    As per the contractor, they are currently executing the construction of both the quay wall and the jetty structure which fall under the project scope while the overall project observed 62% progress.

    Moreover, MTCC had affirmed on completing the installation of precast concrete blocks required for the quay wall structure prior to the actual structure’s construction. Furthermore, the contractor is executing the dredging operations for the harbor basin, which is currently at 57% completion.

    The project scope include, besides the dredging and excavation operations which would span 19,630 cubic meters, the construction of a 31 meter breakwater along with the quay wall and jetty which would measure 136 meters and 138.73 meters respectively.

    In addition to this, MTCC will install a harbor pavement spanning 580 square meters. Meanwhile, the project valuation is a total of MVR19.9 million as reported by the contractor.

     

    Related Posts

    BUSINESS

    Government Expands Subsidized Fuel Stations for Fishermen to Nine Locations

    April 29, 2026
    BUSINESS

    Malé Hospitals Move to Strengthen Backup Power Capacity

    April 29, 2026
    BUSINESS

    Dr. Ali Azwar Takes the Helm at STELCO as New Managing Director

    April 28, 2026
    Leave A Reply Cancel Reply

    Don't Miss
    FINANCE

    State Recovers MVR 800M in Outstanding Revenue

    April 29, 2026

    The Maldives Inland Revenue Authority (MIRA) collected MVR 882 million in overdue state dues last…

    Malé Hospitals Move to Strengthen Backup Power Capacity

    April 29, 2026

    Minister Denies Political Motive Behind Gedhoruveriyaa Housing Delays

    April 29, 2026
    Demo
    Facebook X (Twitter) Instagram LinkedIn Telegram
    • Home
    • BUSINESS
    • PUBLIC SECTOR
    • TRAVEL & TOURISM
    © 2026 Maldives Business Times. by hyvemedia.

    Type above and press Enter to search. Press Esc to cancel.